The way to control maintenance budget in PM.
by : Santosh Satapathy
Maintenance budget
1) Hi, I just see some desperate attempt to know about maintenace budget and control but I hope can clear you all. Budget and control of order can be done to all the order type of sap pm orders functional background
As we know when creating equipment in maintenance master data we are using two work centeres one is location work center and the other one is responsibile work center. The location work center describes the line or area or section of production the equipment belongs and in the order the work center we maintain it maintains the cost per activity we define.
Suppose our maintenance team goes and do some work, say for two hours, so for this activity type what is defined in the controlling will be debited from the production line or section or area as it is maintained in pp. Of cousre when we settle the order and at the same time from the budget that much of fund deducted
Integration Part
a) actually this is done by co people
b) go to trans koab
c) tick the commit management in control indicators
maintain co-partner as semi active
you can maintain other things as maintaenance status and settlement profile
d) you should maintain object class as overhead costs orif you have service module you can do profitably analysis
e) you must maintain collective order without automatic goods movement
f) you can maintain status profile as your wish
g) for residence time i amintaied one month
2) then you have to maintain budget profile
for maintaining budget profile you have to goto trs ok0b
crate a budhet profile these are co people job
3) go to oioa here you assign budget profile to order type
4) in mantain budget profile
time frame -past means how many years past you can plan here start year is the referenace point
same with future
you must tick total values
annual values
exchange rate should be m-standard translation at average rate
activation type should be 1-automaticactivated when budget allocation done
budgeting currency-i choose controlling currency
5) then go to ko22 and assign the budget profile to order or group of order
This is the way I maintain budget for pm orders.