----Original Message-----
Subject: Milestones
We don't use networks and activities.
The same time we want to use milestones only with WBS-elements for basic POC evaluation.
For instance for WBS we can attach several milestones with different POC, like 10%, 50%, 80%.
What is the tool in the system to confirm that particular milestone is reached? How can I change milestone status?
-----Reply Message-----
Subject: RE: Milestones
each milestone attached to a WBS element will have an actual date field open for entery when u release the WBS element. this will determine if the milestone has been achieved or not.
the %age entered in the milestone for POC will be considered in the progress analysis.
-----End of Message-----