If you look at MD04, the rescheduling date is based on the Stocks Requirement date.
It does not take into account the parameters in Procurement and Scheduling in the Material Master.
In the net requirements calculation, the system checks whether warehouse stock or firmed receipts are available to cover requirements. If a material shortage exists, the system usually creates a new procurement proposal.
The rescheduling check is used to change the dates of already existing firmed receipts not planned on the same day as the requirement to suit the requirement date.
For this purpose, the system displays the appropriate exception messages with rescheduling proposals for these firmed receipts to be processed by the MRP controller.
You defined the rescheduling parameters in Customizing for MRP.
An important parameters is the rescheduling horizon period to be included.
1. OPPQ per plant to Carry out overall maintenance of plant parameters.
2. OPPR per MRP group to Carry out overall maintenance of MRP groups.
You can also define tolerance values for the creation of exception messages.
These values define a time period in which no exception message is to be created, despite the fact that a rescheduling proposal may exist.
The MRP controller can thus avoid a situation where too many exception messages are created if a certain buffer has already been planned for scheduling basis dates.
Rescheduling Exception Proposal
Bring process forward (reschedule in)
Within this rescheduling horizon, the net requirements calculation checks whether, after a requirement, a firmed receipt exists, which can be used to cover this requirement. Then the system displays a rescheduling date as well as the exception message Bring process forward for this receipt. The net requirements calculation then uses this receipt and the
system will only create another procurement proposal if the receipt quantity is not sufficient to cover the complete requirement. Several firmed receipts can be used to cover one requirement.
The rescheduling horizon is always calculated from the MRP date.
Postpone process (reschedule out), or cancel process
The net requirements calculation checks over the complete time axis whether availability could still be guaranteed without the receipt in question. If this is the case, the system checks whether the receipt planned here could be used to cover a future requirement. If the system can find such a requirement, it then displays a rescheduling date as well as the exception message Postpone process for this receipt.
If the system finds no future requirement, for which the receipt is required, the system displays the exception message Cancel process.
Wednesday, April 1, 2009
Subscribe to:
Post Comments (Atom)
Archives
-
▼
2009
(347)
-
►
December
(85)
- Problem in Shipping
- Movement Type Posting Error In Delivery
- Shipping Conditions and Storage Location Determina...
- Shipping Unit Tables in SAP SD
- SAP SD Shipping Point
- SAP SD ATP through shipping
- Duplicate customer purchase order
- Default First Date is not Today
- Auto proposed all the dates when creating Sales Or...
- Define whether the Material can be used at which S...
- Assign a Cost Center manually in a Sales Order (VB...
- Sales and Distribution - Transfer of Requirements
- Define Tax Determination Rules
- Taxation Explain with an example
- Return material From customer
- Scheduling Agreement Vs Contract
- SAP SD Sales Order Sales BOM Implementation
- SAP SD Sales Order How to Know that Sales BOM is w...
- SAP SD Sales Order What Is BOM Referring to SAP SD...
- Sales Order Mass Change
- SAP SD Sales Order Release strategy for Sales orde...
- SAP SD Sales Order How to do rebate processing
- SAP SD Sales Order Rebate Process with Ref. to SO
- SAP SD Sales Order Consignment Sales Process
- SAP SD Sales Order Issue free goods to selected Cu...
- SAP SD Sales Order Supressing Fields in Sale Order...
- SAP SD Sales Order Some Light on Batch Determinati...
- SAP SD Sales Order Difference between Item Proposa...
- SAP SD Sales Order Steps for SD Variant Configurat...
- SAP SD Sales Order Process Flow for 3rd Party Sale...
- SAP SD Sales Order Number Ranges In Sales Order
- SAP SD Sales Order What is Debit note and Credit n...
- SAP SD Sales Order Configure Intercompany Stock Tr...
- SAP SD Sales Order Cross Selling : How To Configur...
- Explain about SD sales order cycle?
- SAP SD Inter-company Sales
- Special SD sales processes
- Deletion of SD Sales Documents
- SD Product Allocation Implement the Product Alloca...
- What is the difference between inbound and outboun...
- SAP SD Tax Determination- A doubt
- SAP SD Transportation- Case Study Real Time Scenar...
- SAP SD GAP Analysis
- SAP SD User Exits
- SAP SD Meaning of "FORM KOBED_002" and "FORM KOBEV...
- SAP SD Alternative Calcultation Type
- SAP SD Picking option in display
- Accounting Entries generated during SD Sales cycle...
- SAP SD demand graph in UK
- SAP SD Credit/Debit Memo Request
-
▼
April
(26)
- Tcodes in SAP Project System Part I
- Tcodes in SAP Project System Part II
- Tcodes in SAP Project System Part III
- Transaction Code To View All SAP Tables
- Commonly Used Tcodes in PP Module Part 1
- Commonly Used Tcodes in PP Module Part 2
- Commonly Used Tcodes in PP Module Part 3
- SAP Production Planning Table
- SAP PP Master Data Tables
- Table of the Order Production Operation
- PP Scheduling Rescheduling date does not take into...
- PP Scheduling Schedule Margin Key in Production Sc...
- PP Scheduling Work Scheduling View in Material Mas...
- PP Scheduling Scheduling Background Jobs for MRP
- PP Scheduling What is Finite and Infinite Scheduli...
- PP Scheduling What Is Mean By Schedule Lines
- Rescheduling date does not take into account the G...
- PP Production Order Production Setup Time
- PP Production Order Material Stock in Production O...
- PP Production Order Automatic Conversion to Produc...
- PP Production Order Regarding Production Order Con...
- PP Production Order What is Backflushing?
- PP Production Order How Costing takes place in Pro...
- PP Production Order SAP flow for REWORK activity
- PP Production Order Serial Number For Component
- How To Delete Old PP Production Orders
-
►
December
(85)







0 comments:
Post a Comment